Project Update6th Street North reconstruction project finishes ahead of schedule

Improvements to 6th Street North occurred along the entire roadway within the Project Area

6th Street North reopens Friday, Nov. 4th, ahead of the anticipated completion schedule of late November/early December.

Construction started Monday, June 13, 2016.

The City of Nampa thanks the public for its patience as we improved the roadway and utilities in the area.

The project replaced the waterline and reconstructed the full roadway from 1st Avenue North to 4th Avenue North and 9th Avenue North to 16th Avenue North. Half of the roadway was reconstructed from 4th Avenue North to 9th Avenue North because the waterline in the area was replaced in 2014. The project included the following improvements:

Pedestrians

  • Pedestrian ramps were replaced to meet current standards
  • Flashing push button activated crosswalk signs were installed at the Idaho Arts Charter School

Storm Water

  • Storm water inlets and storm water pipes were replaced
  • Curb and gutter was installed in places where there were none

Water

  • Water and pressure irrigation pipe were replaced
  • Fire hydrants and water services were replaced

Bicycles

  • Shared road markings for bicycles were painted on 6th Street
  • Bike signage was installed

Construction was completed in phases to minimize impacts to residents and motorists.